Competitive tendering evaluation

FOI reference - FOI-106
Date - 18 April 2023

Request

You have requested the following information:

“For any last ten tenders awarded through competitive tendering in the last two years that were evaluated separately on price and quality, please provide the scores of all evaluated bidders for both price and quality, as a proportion of the total possible score for each category. Bidders need not be named.”

Response

I confirm that we hold the information you have requested.

Procurement 1

Supplier Total
Technical
(Quality)
Total
Commercial
(Price)
Total
Supplier 1 38.60% 24.69% 63.29%
Supplier 2 51.00% 25.00% 76.00%
Supplier 3 51.00% 24.34% 75.34%
Supplier 4 44.70% 24.96% 69.66%

Procurement 2

Technical score %
Tenderer (Quality) Price
Score %
Total
Score%
Final
Ranking
Supplier 1 69.40 16.15 85.55 1
Supplier 2 50.00 20.00 70.00 2
Supplier 3 57.40 10.79 68.19 3
Supplier 4 52.00 3.18 55.18 4
Supplier 5 36.00 11.64 47.64 5

Procurement 3

Supplier Total
Technical
(Quality)
Total
Commercial
(Price)
Grand
Total
Supplier 1 6.00% 12.47% 18.47%
Supplier 2 40.00% 60.00% 100.00%

Procurement 4

Supplier Total
Technical
(Quality)
Total
Commercial
(Price)
Total Total
Presentation
(Quality)
Grand
Total
Supplier 1 51.00% 13.60% 64.60% 16.00% 80.60%
Supplier 2 46.00% 9.87% 55.87% 12.00% 67.87%
Supplier 3 46.00% 7.81% 53.81% 8.00% 61.81%
Supplier 4 33.00% 20.00% 53.00%    
Supplier 5 39.00% 13.63% 52.63%    
Supplier 6 40.00% 6.68% 46.68%    
Supplier 7 39.00% 5.25% 44.25%    
Supplier 8 38.00% 5.02% 43.02%    
Supplier 9 29.00% 12.73% 41.73%    
Supplier 10 23.00% 16.04% 39.04%    

Procurement 5

Supplier Total
Technical
(Quality)
Total
Commercial
(Price)
Grand
Total
Supplier 1 32.00% 60.00% 92.00%
Supplier 2 29.00% 1.84% 30.84%
Supplier 3 23.00% 5.90% 28.90%
Supplier4 23.00% 1.22% 24.22%

Procurement 6

Evaluation
Criteria
Total
Technical
(Quality)
Total
Commercial
(Price)
Grand
Total
Supplier 1 58% 14% 72%
Supplier 2 42% 14% 56%
Supplier 3 72% 20% 92%
Supplier 4 50% 14% 64%
Supplier 5 51% 13% 64%

Procurement 7

Supplier Total
Technical
(Quality)
Total
Commercial
(Price)
Total
Presentation
(Quality)
Grand
Total
Supplier 1 45.00% 40.00% 6.00% 91.00%
Supplier 2 27.00% 19.43% 8.00% 54.43%

Procurement 8

Supplier Total
Technical
(Quality)
Total
Commercial
(Price)
Total
Presentation
(Quality)
Grand
Total
Supplier 1 42.00% 30.50% 6.00% 78.50%
Supplier 2 30.00% 40.00% 8.00% 78.00%
Supplier 3 38.00% 31.55% 8.00% 77.55%

Procurement 9

Supplier Total
Technical
(Quality)
Total
Commercial
(Price)
Grand
Total
Supplier 1 32.00% 49.06% 81.06%
Supplier 2 20.00% 60.00% 80.00%
Supplier 3 32.00% 37.63% 69.63%
Supplier 4 23.00% 42.45% 65.45%
Supplier 5 32.00% 29.00% 61.00%
Supplier 6 31.00% 28.04% 59.04%
Supplier 7 20.00% 20.82% 40.82%

Procurement 10

Evaluation criteria Weighting Supplier 1 Supplier 2 Supplier 3 Supplier 4
Technical (Quality) weighted score 70% 42.00 37.00 49.00 56.00
Price weighted score 30% 23.65 30.00 24.33 27.15
Total weighted score 100% 65.65 67.00 73.33 83.15
Overall ranking   4 3 2 1